What's Happening Now?
- Construction is underway! Below are some project milestones:
July 2026:
- An existing distribution line will be relocated from the north side of North Road to the south side of North Road.
- Crews will drill foundations for new transmission structures along Chumstick Highway and existing transmission lines.
- Contractors will prepare for installation of underground electrical lines.
August 2026:
- Excavation of footings for the transformer, control building, and switchgear are occurring inside the substation yard.
September 2026:
Concrete is poured in the excavated footings in preparation for placement of the transformer, control building, and switchgear.
October 2026:
Using a crane, the transformer, control building, and switchgear are placed inside the substation yard.
What to Expect:
During construction, you may notice:
- Flagger controlled traffic and occasional lane restrictions on Chumstick Highway
- Temporary trail closures or pedestrian detours
- Construction equipment and daytime construction noise
- Temporary changes to parking or business access near active work areas
Over the duration of the construction, planned power outages may be necessary. Affected customers will be notified in advance of any planned power outage.
Questions? Contact us at
[email protected] or call 509-661-8563.