HAPPENING NOW - FALL 2024
- FDT-230 - Construction activities on the main electrical line and fiber cable installation were completed in September.
- FDT-150 - Design is progressing and we will start contacting property owners to obtain necessary easements. If you receive an easement letter, please complete and return as soon as possible. Pending acquisition of easements, construction activities are expected to begin in this area in early 2025. Please note: Design in some areas may change as the project progresses. Additional or revised easements may be needed.
- FDT-151 - Construction on the main electrical line started in August and is expected to continue through the end of the year.
The area from the Yacht Club south to just before the intersection with Navarre Coulee Road is currently in the 3-5 year plan for fiber expansion. We will begin reaching out once we reach the Preconstruction Phase for this area.