Springwater Substation

Wenatchee Foothills

Background

Chelan County PUD is seeking a location for a new substation to serve the West Wenatchee area. The existing substations currently serving the area are nearing capacity. A new substation is needed to redistribute existing electrical load and serve future growth and development. We are committed to involving the public in the substation siting process. 

Stay Engaged!

Email us to be added to our distribution list for updates throughout the project. 

Questions?

Please email customeroutreach@chelanpud.org or call 509-661-8563.

Neighborhood Meeting - DECEMBER 10

Chelan PUD will host a neighborhood meeting to provide an update on the substation being explored on WSU's property. Property owners and customers neighboring the WSU Tree Fruit Research Center at Springwater and Western avenues in Wenatchee have been invited. If you did not receive a postcard mailer or email and would like to stay involved, please email customeroutreach@chelanpud.org.

Tuesday, Dec. 10 - 5:30pm
WSU TRFC, 1100 N. Western Ave.

What's happening now - FALL 2024:

  • PUD staff, in coordination with the property owner (WSU), further explored Sites 1A and 3 based on stakeholder feedback. This included more specific layouts and access for the substation and associated power lines.
  • Based on this exploration, the PUD is narrowing in on a variation of Site 1, referred to as Site 1CStaff continues to perform analysis and feasibility on the site.
  • PUD staff will be hosting a neighborhood meeting with adjacent property owners in December. 
  • May 20, 2024 - Update to PUD Commissioners (link to audio, presentation begins at 1:03)

2023:

In 2023, PUD staff listened to stakeholder feedback and continued work on narrowing in on a site for the future substation to serve the west Wenatchee area.

  • We presented four potential sites (1A, 1B, 2, and 3) within WSU's property at the corner of Springwater and Western avenues.
  • We evaluated each site based on stakeholder feedback, system, land, and environmental considerations.
  • We used the Evaluation Matrix to evaluate (score) each site on the basis of system, land, and environmental considerations. We then asked stakeholders for feedback on aesthetics and neighborhood values using this survey
  • Detailed view of potential sites: 1a1b23.
  • Feb. 21 neighborhood meeting slide
  • Site Evaluation Matrix (June 2023) - incorporates public feedback on Aesthetics and Neighborhood Values.

Anticipated Project Timeline

*This timeline is subject to change as priorities shift and adjustments are made to the schedule.

West Wenatchee Substation Timeline